Choice of communication pipeline routing

Update:2020-04-10   View(s):943   Keywords : pipeline routing

The construction of communication pipelines generally follows water, electricity, gas, heating, and pollution in urban planning. With the improvement of people's understanding of communication resources and the closeness of the relationship between people and communication systems, communication facilities will also be one of the necessities of people's lives.

 

(1) On the premise of satisfying the design, choose to build on the route through which the backbone network resources pass.

 

(2) In order to reduce overhead pole roads, full consideration should be given to the construction of branch roads and pipelines, and to improve the flexibility of the road network.

 

(3) Combined with the urban development plan, according to the planning and allocation of the urban municipal construction department, carry out reasonable construction.

 

(4) Prioritize the use and combination of existing pipeline resources, reduce the scale of construction investment, and increase resource utilization.

 

(5) Planning and construction should avoid large-scale facilities gathering areas, such as railways.

 

(6) It is not suitable to build pipelines in the sections that have a significant impact on the foundation. There are rivers, subsidence areas, swamps, sandy soil, and high water levels.

 

(7) Pipeline construction should also adhere to the principle of shortest routing.

 

(8) Pipeline construction must go through on-site inspections and must maintain a sufficient clear distance from other buildings or facilities.

 

(9) The pipeline construction must maintain a certain slope to facilitate the discharge of foreign objects that affect the safety of the pipeline.

 

(10) The buried depth of the pipeline should be combined with the height of the manholes on both sides, but the height difference should be kept within a reasonable range.

 

(11) S-curves and U-curves shall not appear in the pipeline section.